Charleston Air Force Base
Repair Electrical Distribution Areas
A, B, C, D, E, F, G, H, I J, & K

Owner/Reference
Charleston Air Force Base

Completion Date
Ongoing

Cost of Construction
$21,400,000

Firm Responsibilities
Electrical Engineering

The project entailed designs for the replacement / upgrade of underground systems on the Charleston Air Force Base. Design encompassed the replacement of a 12.47kV overhead electrical services and communication wiring with underground distribution system in Areas A, B, C, D, E, F, G, H, I J, & K. The project consisted of multiple pad-mounted switches and transformers as well as, encompassed nearly 6 miles of duct bank and distribution conductors. Over head services to buildings were also replaced with underground services.

Other Areas:

  • Chapel Renovation
  • Children Development Center
  • Airfield Lighting
  • Building 16000 Headquarters Renovation
  • Building 225 Add/Alter Fitness Center
  • Building 532 Repair Aircraft Maintenance Facility
  • Building 544 Upfit Aircraft Maintenance Facility
  • Building 178 Alter/Repair Freight Loading Terminal
  • Building 201 Repair TWCF OPS
  • Building 302 Alter/Repair Communications Administration Facility
  • Building 2000 Fire Suppression System
  • Building 652 Add/Repair 315th Reserve CE Facility
  • Building 626 Upgrade Hazardous Material Storage
  • Building 164 Repair Passenger Terminal Building
  • Building 536 Alter/Repair NDI Maintenance Facility
  • Building 171 Repair AFRC APS Training Facility
  • Building 108 Repair Flight Simulator Facility
  • Building 707 Repair PMEL Facility
  • Building 248 Repair Flight Crew Facility
  • Building 164 Alter/Repair Passenger Terminal
  • Building 322 Convert Dormitory to Office Building
  • Building 221 Renovations to Community Activity Center